Louisiana megaprojects tracker

Tracking megaprojects across Louisiana

19 projects worth more than $300 billion, from SpaceX's launch site in Vermilion Parish to the LNG terminals on the Gulf. Select a project to see where it stands and what it will buy.

major projects
19
announced investment
$300B+
funded or under construction
8

Statuses checked November 2, 2026. Sites are approximate.

Select a project to see where it stands. Drag to move the map, right drag to turn it, and scroll to zoom.Tap a project to see where it stands. Drag to move, pinch to zoom, and twist to turn.

All 19 projects

Grouped by sector. Select a project to see it on the map.

Spaceport

SpaceX expects to start construction in 2027.

  • Unveiled August 2026. Construction expected in 2027, first launch as soon as 2029. Louisiana Economic Development

AI data centers

Meta, Hut 8, and Applied Digital are building now. Amazon's campuses are next.

  • Broke ground December 2024. More than $1.6 billion contracted with Louisiana businesses so far. Contractors: Turner, DPR, Mortenson. Louisiana Economic Development

  • Three campuses unveiled February and August 2026. Construction was slated to start March 2026. Contractors: STACK Infrastructure. WBRZ

  • Broke ground October 2026. Operations expected in the second quarter of 2027. Contractors: Jacobs. Louisiana Economic Development

  • Site work since January 2026. Operations expected mid 2027. WBRZ

Power for data centers

Three plants are under construction. A vote on more is expected in December 2026.

  • Public Service Commission vote expected December 2026. Three earlier plants broke ground December 2025. The Lens

LNG export terminals

CP2, Louisiana LNG, and Commonwealth are building now. Plaquemines and Argent target investment decisions in 2027.

  • Both phases funded. First LNG expected in the second half of 2027. Contractors: Worley. Venture Global, via SEC filing

  • Federal applications filed late 2025. Investment decision targeted for the first half of 2027. Gas Processing News

  • Investment decision April 2025, about 28% complete by mid 2026. First LNG expected 2029. Contractors: Bechtel. Offshore Engineer

  • Decision made May 2026. Operations expected 2030. Contractors: Technip Energies. gCaptain

  • Partial export approval July 2026. Investment decision targeted 2027, first LNG 2030. Contractors: Tecnimont (design), Baker Hughes, CB&I. Argent LNG

  • Redesigned to one new train. No investment decision yet. Contractors: Bechtel. Cameron LNG

Steel, chemicals, and fuels

Hyundai Steel and Blue Point are building now. The others await permits or investment decisions.

  • State permits issued 2025 and challenged in court. No investment decision yet. Contractors: McDermott (design). Ascension Economic Development Corporation

  • Broke ground September 2026. Startup expected 2029. Louisiana Economic Development

  • Broke ground August 2026. Operations expected 2029. Contractors: Technip Energies. Hydrocarbon Engineering

  • Unveiled March 2026. First phase targeted for 2030. Hydrocarbon Processing

  • Air permit issued, water permit and financing pending. Louisiana Economic Development

  • No investment decision yet. Production expected around 2030 or later. Contractors: Samsung E&A. Louisiana Economic Development

Ports

The federal permit was issued in August 2026. Opponents have promised a legal challenge.

  • Federal permit August 2026. Opponents have promised a legal challenge. KPLC

See where AI pays off in your operation

One working session with your leadership team. We'll tell you plainly where custom AI pays off and where it doesn't.

Book a free AI assessment
  • Free AI assessment
  • Fixed price pilots
  • Supported for the long haul